Eildon Reserves Redevelopment

  • Project typeRecreation Project
  • Project value$6.1 million
  • Project scheduleIn Progress
  • Completion Date20 December 2024
Eildon Splash and Skate Park.jpg

Works are underway on the much-anticipated Eildon Reserves Redevelopment.

The project will see the redevelopment of Walter Moore and Thomas Marr Reserves in Eildon and involves a range of different elements, which are outlined in the below construction schedule.

Project Element Status  Estimated Completion Date
Skate Park Complete Completed in May 2024
Flying Fox and Swing Set Playground  Works in Progress  Completed in October 2024
Senior Play Space Works in Progress Completed in October 2024
Adventure Playground Works Scheduled 28 February 2025
Splash Park Works Scheduled 25 January 2025
Toilet and change facilities Works in Progress 20 December 2024
BBQ and Shelter Works Scheduled 20 December 2024
Fencing Works Scheduled 20 December 2024
Minor Footpath and Landscaping Works  Works Scheduled 20 December 2024

The public toilet is undergoing a significant upgrade, providing access for all abilities and incorporating a new change area, and is closed until the upgrades are complete. The nearest alternative public toilets can be found at Eildon Lions Park. 

As part of the project, Utah Place is also becoming a no-through road, based on community feedback, providing a safe pedestrian link for users, particularly families with young children moving between the two reserves.

This $6.1 million project is made possible with funding from State Government’s Regional Tourism Investment Fund, Local Sport Infrastructure Fund and Changing Places Fund, and the Federal Government’s Local Roads and Community Infrastructure Fund. Council’s $1.493 million contribution includes the proceeds from the future sale of two parcels of underused land in the Eildon township.