Gravel Roads Resheeting Program 2024/25

  • Project typeRoadworks
  • Project value$670,000
  • Project scheduleComplete
  • Completion Date30 April 2025

The 2024-2025 Gravel Roads Resheeting Program is underway. Through this initiative, a selection of gravel roads within Murrindindi Shire will undergo renewal, enhancing the quality and longevity of the road infrastructure.

Below is a list of the roads scheduled for resheeting, along with the planned week for each project (weather permitting).

If you would like to check whether these works will affect access to your property, please use the links provided next to each road name. For a broader view of the scheduled works and locations, please refer to the map below.

Location Status Expected commencement date (week commencing)    Location 
Steuarts Rd (South), Glenburn Complete 2 December 2024 View exact location
Nichols Rd, Narbethong - Buxton  Complete

24 March 2025 (S1)
28 March 2025 (S2)

View exact location
Dicks Rd, Acheron  Complete 14 April 2025 View exact location
Larnoo Rd, Ghin Ghin Complete 10 March 2025 View exact location
Margetts Rd, Flowerdale - Yea Complete 24 Feb 2025 View exact location
Deepdene Rd, Yea Complete 3 March 2025 View exact location
Silver Parrot Rd, Flowerdale Complete 17 Feb 2025 View exact location
O'Gradys Rd, Pheasant Creek Complete 27 Jan 2025 View exact location
Jouvelet St, Kinglake West Complete 3 Feb 2025 View exact location
Extons Rd, Kinglake Central Complete 27 Jan 2025 View exact location
Oak Gr, Kinglake Complete 17 Feb 2025 View exact location
Keith St, Kinglake Complete 10 Feb 2025 View exact location
Sycamore Gr, Kinglake Complete 10 Feb 2025 View exact location
Royal Cres, Kinglake Complete 17 Feb 2025 View exact location
Whittlesea-Yea Rd S/R, Flowerdale Complete 17 March 2025  
Lawrey Rd, Kinglake Complete 31 March 2025  
Spring Creek Road, Fawcett Complete 31 March 2025  
Back Eildon Road , Thornton (Section 1) Complete 5 May 2025 View exact location
Back Eildon Road , Thornton (Section 2) Complete 5 May 2025 View exact location
Acheron Road, Acheron Complete 12 May 2025 View exact location