Culvert Component renewals and repairs in various locations around the Shire are currently underway. Through this initiative, works will be undertaken on various culverts, enhancing the quality and longevity of the existing stormwater drainage network.

For Dairy Creek Road Culvert No 3, a temporary road closure is required to allow the resetting of the culvert. A 2-minute detour will be in place. Please note that local traffic will still be able to access properties. See below for additional details.

For a broader view of the scheduled works and locations, please refer to the map below.

If you would like to check whether these works will affect access to your property, please use the links provided next to each road name. For a broader view of the scheduled works and locations, please refer to the map below.

Location Status Expected commencement date (week commencing) Location
Dairy Creek Rd Culvert No 3  Underway  29 June 2025 View Exact Location
Dairy Creek Rd Culvert No 2 Complete 19 May 2025 View exact location
UT Creek Rd Culvert No 2 Complete

26 May 2025

View exact location
Acheron Road Culvert  Complete 2 June 2025 View exact location