Pathway Upgrades & Repairs Program 2025-2026

  • Project typeRenewal Project
  • Project value$300,000
  • Project scheduleIn Progress
  • Completion Date30 January 2026

Footpath repairs within the Alexandra, Eildon, and Yarck Townships are currently underway. Through this initiative, various asphalt and concrete footpaths will be repaired and/or remediated - enhancing the quality and longevity of the Footpath network and providing DDA required improvements where needed.

Access to businesses and residential homes will be maintained throughout the works.

For a broader view of the scheduled works and locations, please refer to the map. Below is a list of the roads scheduled for works, along with the planned week for each project (weather permitting).

Location Status Expected commencement date (week commencing)
Perkins Street, Alexandra Scheduled 12 November 2025
Downey Street, Alexandra (Grant Street to Endeavour Petrol Station) Scheduled

19 November 2025

Walter Moore Reserve, Eildon Scheduled 10 December 2025
Maroondah Highway, Yarck Scheduled

12 January 2026